Complete fuzzy scheduling and fuzzy earned value management in construction projects

Abstract: This paper aims to present a comprehensive proposal for project scheduling and control by applying fuzzy earned value. It goes a step further than the existing literature: in the formulation of the fuzzy earned value we consider not only its duration, but also cost and production, and alternatives in the scheduling between the earliest and latest times. The mathematical model is implemented in a prototypical construction project with all the estimated values taken as fuzzy numbers. Our findings suggest that different possible schedules and the fuzzy arithmetic provide more objective results in uncertain environments than the traditional methodology. The proposed model allows for controlling the vagueness of the environment through the adjustment of the α-cut, adapting it to the specific circumstances of the project.

Key words: Construction, Earned value method (EVM), Fuzzy logic, Fuzzy set, Project management, Scheduling


Share this article to: More

Go to Contents

References:

<Show All>

Open peer comments: Debate/Discuss/Question/Opinion

<1>

Please provide your name, email address and a comment





DOI:

10.1631/jzus.A1100160

CLC number:

TU71

Download Full Text:

Click Here

Downloaded:

4654

Clicked:

8447

Cited:

11

On-line Access:

2012-01-04

Received:

2011-06-10

Revision Accepted:

2011-09-07

Crosschecked:

2011-12-06

Journal of Zhejiang University-SCIENCE, 38 Zheda Road, Hangzhou 310027, China
Tel: +86-571-87952276; Fax: +86-571-87952331; E-mail: jzus@zju.edu.cn
Copyright © 2000~ Journal of Zhejiang University-SCIENCE