Dynamic time-cost-quality tradeoff of rockfill dam construction based on real-time monitoring
Abstract: Time, cost, and quality are three key control factors in rockfill dam construction, and the tradeoff among them is important. Research has focused on the construction time-cost-quality tradeoff for the planning or design phase, built on static empirical data. However, due to its intrinsic uncertainties, rockfill dam construction is a dynamic process which requires the tradeoff to adjust dynamically to changes in construction conditions. In this study, a dynamic time-cost-quality tradeoff (DTCQT) method is proposed to balance time, cost, and quality at any stage of the construction process. A time-cost-quality tradeoff model is established that considers time cost and quality cost. Time, cost, and quality are dynamically estimated based on real-time monitoring. The analytic hierarchy process (AHP) method is applied to quantify the decision preferences among time, cost, and quality as objective weights. In addition, an improved non-dominated sorting genetic algorithm (NSGA-II) coupled with the technique for order preference by similarity to ideal solution (TOPSIS) method is used to search for the optimal compromise solution. A case study project is analyzed to demonstrate the applicability of the method, and the efficiency of the proposed optimization method is compared with that of the linear weighted sum (LWS) and NSGA-II.
Key words: Dynamic time-cost-quality tradeoff, Rockfill dam construction, Real-time monitoring, Decision preferences
创新点:1. 提出基于面板堆石坝施工质量实时监控技术的施工进度、质量和成本动态预测方法;2. 提出施工决策偏好动态量化方法;3. 提出施工进度-质量-成本多目标均衡求解算法。
方法:1. 通过分析实时监控数据,更新仿真模型参数,仿真得到施工进度,再推导出质量和成本(图4、公式(8)和(10));2. 采用层次分析法,动态量化施工过程中的管理者决策偏好,得到进度-质量-成本三目标间的权重(图5);3. 采用改进的带精英策略的非支配排序遗传算法(公式(13)),求解动态均衡问题的Pareto解,并运用逼近理想解的排序法筛选出最优折衷方案(图5)。
结论:1. 基于实时监控进行施工进度、质量和成本的动态预测,提高了均衡结果与实际施工过程的一致性;2. 动态量化决策偏好,并在优化求解中予以考虑,有助于最优折衷方案的筛选;3. 在施工过程中任意阶段开展的施工进度-质量-成本动态均衡适应了施工条件的动态变化,可有效指导现场施工管理。
关键词组:
References:
Open peer comments: Debate/Discuss/Question/Opinion
<1>
DOI:
10.1631/jzus.A1600564
CLC number:
TV512
Download Full Text:
Downloaded:
3403
Clicked:
4954
Cited:
0
On-line Access:
2024-08-27
Received:
2023-10-17
Revision Accepted:
2024-05-08
Crosschecked:
2016-12-23